XIAOPAI · Wenzhou Xiaopai Electric Power Technology Co., Ltd. · Zhejiang, China
XIAOPAI - Wenzhou Xiaopai Electric Power Technology - builds oil-immersed and dry-type transformers in Wenzhou, Zhejiang, and ships them to distributors and utilities across South America and Africa. Most buyers see the quotation and the photo. The part that decides whether the unit still runs a decade later is everything between the steel coil and the dock. This is that part, written down.WHAT XIAOPAI MANUFACTURES
XIAOPAI manufactures two transformer families for export. The oil-immersed power transformer runs up to 230 kV / 200 MVA and suits substations, industrial plants and utility networks. The dry-type (cast-resin) transformer suits indoor, urban and fire-sensitive sites. Both are built against IEC 60076 as the base standard, and a reference oil-immersed unit has already been delivered to a customer in Spain - which confirms the export chain from our workshop to a European port end to end. See the oil-immersed transformer and dry-type transformer product pages for the rated ranges.

INSIDE THE MANUFACTURING PROCESS
The steps are not exotic. What separates a unit that lasts from one that fails is how tightly each is controlled. Core. Low-loss silicon-steel laminations are stacked and clamped with burr control, because core loss is set here, not later. Windings. HV and LV are wound from foil and wire with the specified clearances and transpositions, then checked for turns ratio before the next stage. Tank and frame. The tank is fabricated, cleaned and leak-tested; for dry-type units the enclosure is built to the site class instead. Vacuum drying. The active part is dried under vacuum so moisture does not sit inside the insulation when the unit is sealed. Oil filling. On oil-immersed units, dried insulating oil is filled under vacuum to keep gases and moisture out of the winding. Assembly and fitting. Bushings, tap changer, terminals and nameplate go on last, and the unit is dressed before it moves to test.QUALITY CONTROL BEFORE EXPORT
Every transformer is routine-tested before it leaves the works: turns ratio, winding resistance, insulation resistance, applied and induced over-voltage, and - for dry-type units - partial discharge. The routine test is the one a buyer can actually witness at our plant; type tests are available on request against IEC 60076. XIAOPAI holds a conformity assessment (INTERTURK) against the EN 60076 series under the LVD and EMC directives, valid to 2031. The testing discipline behind those checks is laid out in depth at Electrical Engineering Portal, which covers how routine and type tests are run on power transformers.EXPORT DOCUMENTATION AND INCOTERMS
XIAOPAI exports mainly on FOB terms, with the buyer's nominated forwarder collecting from Ningbo, Shanghai or Chongqing. The document set we prepare covers the commercial invoice, the packing list and the certificate of origin; the exact Incoterm - FOB, CIF or CFR - is fixed at order stage so responsibility for freight and insurance is unambiguous from the start. A clean document set is what keeps a transformer moving through a destination port instead of sitting in a bonded warehouse. The broader specification frame those documents reference is the IEC 60076 family, covered in the compliance guide at Electrical Engineering Portal.PACKAGING FOR LONG TRANSIT
Ocean freight to South America and Africa runs in weeks, not days, and a transformer is unforgiving of moisture and shock. Export packing uses a moisture-barrier wrap with desiccant, shock-absorbing blocks, and a seaworthy crate sized to the unit. Bushings and accessories travel in a separate labelled carton so they are not crushed against the core. The point is plain: the unit that arrives should be the unit that left.LOGISTICS TO SOUTH AMERICA AND AFRICA
Shipments leave from Ningbo, Shanghai or Chongqing and route to destination ports across the two regions. Transit time depends on the port pair and the sailing, so it is confirmed against the booking rather than quoted as a fixed number. What we can state up front is the packing method, the document set and the Incoterm - the three things that decide whether the unit clears the destination smoothly.AFTER-SALES SUPPORT
A transformer is a long-life asset, so support does not stop at the dock. XIAOPAI supplies a spares kit matched to the unit, remote guidance for commissioning, and coordination with local service contacts where the buyer has them. The routine-test records travel with the unit, so a later fault can be traced back to the as-tested baseline instead of guessed.WHAT TO ASK BEFORE THE ORDER
Four questions settle the export side of a transformer order. Which routine tests will you witness, and which type tests do you need on file - the routine set is standard; type tests are the ones buyers often forget until the port asks. What Incoterm applies, and who arranges freight and insurance - FOB, CIF and CFR move the risk line, and the contract should say which. How is the unit packed for ocean transit, and what is in the spares kit - weeks at sea decide this, not the showroom. Who holds the destination certificate, and is pre-shipment verification required - the answer changes from one country to the next, and the supplier should lay it out before the order is drawn.ONE LINEXIAOPAI - Wenzhou Xiaopai Electric Power Technology manufactures oil-immersed power transformers up to 230 kV / 200 MVA and dry-type transformers in Zhejiang, China, and works with long-established Chinese manufacturers for the flexible-packaging equipment line. Product pages:
oil-immersed transformer ·
dry-type transformer.